Concurring Opinion 24 G.R. Nos. 271059, 271347,
E-02472,and E-04036
HON. DIOKNO:
Definitely, Your Honor. Because, as I said, any project delays is costly. For
example, they remove funding for the subway system that's supposed to be finished
by 2029, right-of-way appropriation for the subway, and also the North-South Rail
System, they removed and they put it under unprogrammed. That will cause a delay
of at least five years in the implementation of that project. At the same time, because
it's delayed, then we have to pay what is called c·ommitment fee to the lending
agency, and that's usually around quarter of l %.76
Hence, inasmuch as Congress retains the discretion to transfer PAPs
from programmed to unprogrammed, and vice versa, it cannot exercise such
discretion to the extent of already violating the government's valid and
existing obligations. This does not only result to actual monetary penalties but
may also affect the reputation of the Philippines as a contracting pai1y both
locally and internationally.
ACCORDINGLY, I concur.
7
1<, Oral Arguments, TSN, Hon. Benjamin E. Oiokno, April 7, 2026, pp. 11 2- 11 3.