Court decisionSource checked
271059/271347/E-02472/E-04036 Concurring and Dissenting Opinion: Justice Jhosep Y. Lopez — Official PDF
271059/271347/E-02472/E-04036 — Promulgated October 7, 2026 · 2026 · Supreme Court 2026 / Separate opinion
Source checked. The source check identifies the document; it does not verify every transcribed word or its current legal effect. Recovered or scanned text may contain errors. Compare the wording and subsequent history with the linked legal source.
DIGITAL P. 35 / 36
Concurring and Dissenting Opinion 35 G.R. Nos. 271059, 271347,
E-02472 &E-04036
accountability, involving as it does the national budget, which is meant to be
a tool for policy furtherance and national development.
The provision on unprogrammed appropriations in the national budget
came into existence more than four decades ago and has been continuo1,1sly
adopted by every administration. 127 As explained above, it is a form of standby
appropriation for emergencies and. contingencies, such as unexpected
expenses and additional support for infrastructure projects, social programs,
• and foreign-assisted projects.
To be sure, the wisdom of the inclusion of unprogrammed
appropriations in the national budget is a policy question that is properly
lodged with the political departments pursuant to their constitutionally
mandated duties and powers. Be that as it may, I submit that unprogrammed
appropriations remains to be a legal concept that is subject to relevant
constitutional and statutory constraints, to the end that its inclusion in the
national budget remain truthful for the purpose for which it was created.
First, given the rationale behind its conception, items under
unprogrammed appropriations are designed to be limited to P APs for
emergencies and contingencies, and to priority development programs, which,
for lack of definite funding only, could not be yet included in programmed
appropriations. Notably, the determination of these programs may be done by
the Legislative-Executive Development Advisory Council (LEDAC), which
• is an advisory and consultative body created by R~public Act No. 7640,
• headed by the President and composed of members of Congress, the very
function of which is to ensure consistency in coordinating executive
development planning and congressional budgeting. Indeed, the LEDAC is
expressly mandated under Republic Act No. 7640 to "bring about effective
integration of the priority development programs and projects proposed by
regional, provincial and other local development councils into .the national
development plan, within the constraints of the national budget[.]" Thus,
during budget deliberations, the Congress may rely on the findings and report
of the LEDAC in this respect to ensure that any a.111endments made to the
President's budget proposal is consistent with the executive's priority
development plan. On this note, the order of priority of the PAPs to be funded
under unprogra..rnmed appropriations once the conditions are reached, must be
determined and clearly stated in the GAA. The authority to determine or
modify the order of priority may nevertheless be delegated to the, President,
subject to the criteria set by Congress.
127 DBM Ready to Defend the NEP; For:nrnla observed, no irregularity in allocating unprogrammed funds,
DBM \Vebsite, available at https:/l\vww.dbm.gov.ph/index.php/management-2/426-dbm-ready-to-
defend-uep-fonnula-observed-no-irregu!arity-in-allocati.ng-unprogramrned- . .
funds#:-:text=Wisdom%20of}t20Unprogramrried%20Appropriations,unprogrammed%20appropnat10 ~
n°/o20wi11%20be.0420triggered, last accessed on November 5, 2025. /